DR Horton seeks to shift Skye townhomes downhill to Timp Highway

by | Oct 26, 2026

The nation’s largest homebuilder wants to move a block of townhomes planned for the hillsides of its Skye development in north Lehi down to land along Timpanogos Highway, a change that would let more housing go into the master plan’s mixed-use district without increasing the project’s overall unit count.

The proposed amendment to the Skye Area Plan would turn the Mixed Use 1 area’s fixed allotment of 517 equivalent residential units into a range of 517 to 627.

Any units added there would have to come out of other parts of the 1,728-acre plan, which remains capped at 2,736 units. The amendment also converts four of the plan’s nonresidential units to residential, bringing the split to 2,460 residential and 276 nonresidential.

The Lehi City Council took up the amendment at its Oct. 13 meeting. The Planning Commission forwarded a positive recommendation on Sept. 24 on a 4-1 vote. No one spoke during the public hearing.

“What we’re seeking today is not to increase any [units] anywhere. Nor are we seeking to change commercial [units] to residential [units],” the DR Horton representative said last week.

Instead, the company is looking to rearrange the makeup of housing types within the complex development agreement.

Why move the units?

Mixed Use 1 straddles Center Street on the north side of SR-92 (Timpanogos Highway). According to the city staff report, DR Horton’s Inverness Preliminary Plat E brings the area close to its 517-unit allotment, while one parcel along the highway still has nothing proposed on it. Depending on what kind of commercial lands there, staff wrote, the area could exceed the cap.

Inverness Preliminary Plan E, also on the Oct. 13 agenda, shows 405 townhomes on 36.76 acres, about 11 units per acre.

Staff framed the shift as a potential benefit: fewer homes higher on the hillside and more near the highway, which the report says would reduce congestion on local roads and environmental risks to homes.

At the Planning Commission, Scott Bishop, representing DR Horton, said the builder is purchasing roughly 38 acres and residential units previously held by Gardner Group.

He said the proposal would relocate about 98 townhome units from upper Inverness to Mixed Use 1 and replace some upper-area townhomes with single-family homes, without increasing the plan’s total units or townhome count.

The engineering studies submitted with the application analyze a smaller shift: 110 units moved out of the upper pods known as MD13 and LD6.

An exhibit attached to the water study says 98 ERUs are planned to move, with 110 used as the maximum for analysis. In August, the city’s Development Review Committee had asked for utility and traffic studies on the effect of adding up to 200 units to Mixed Use 1.

DR Horton has been working to develop the land that was originally owned by Micron for a manufacturing and office concept in the Utah County town that’s home to much of the Silicon Slopes tech sector. Micron later sold land to Texas Instruments.

Email Taylor Anderson